13314 Buckland Hall  •  Job Book Sections
Client Contact Info
Sherin Bruning
  • Phone: 314-651-6598
  • Email: Sherin.Bruning@gmail.com
Ryan Bruning
  • Phone: TBD
  • Email: TBD

Subcontractors, Partners & Contacts
Beck/Allen CabinetryKristine Factor
Fireplace & Grill CenterMatt Hartman
SGO Designer GlassRick Hecht
SFI (Stone Fabricator)
Wine CoolerDaron Deen
Interior DesignerEmily Castle

Project Phases — Overview
⚠ LOTS OF TEMPORARY PROTECTION — DAUGHTER HAS SEVERE ALLERGIES TO DUST!
Phase 1
  • Wall moldings to be laid out and applied
  • Fireplace moldings to be applied
  • Determine mantel legs with Ryan
  • Drop ceiling in bar
  • Demo bar and vanilla box it out. Cover it and wait till the cabinets come in
  • Rough in plumbing and lighting?
  • Replace glass in bar window
  • Fireplace stone, mantle trim build-up and doors
  • SFI templating FP 7/30
  • Paint walls
  • Determine Exterior work scope and bid
🔍 Grill area, deck and pool need to be explored on site during Phase 1 — see the Exterior / Deck / Pool section below.
Phase 2
  • Install Bar cabinets, countertop, sink, faucet, plumbing, wine fridge and electrical finish
  • Start exterior work
Phase 3
  • Install doors upon arrival
  • Install exterior door hardware at lanai

Great Room / Family Room — Scope of Work
Great Room / Family Room
  • Demo bar and vanilla box it out. Cover it and wait till the cabinets come in
  • Drop ceiling in bar
  • Replace glass in bar window
  • Fireplace stone, mantle trim build-up and doors
  • Living room - Wall molding
  • Refer to Emily's drawing
  • Keep existing Chairrail and molding
  • Use same 3 1/4" chairrail molding to create applied wall panels
  • Emily's drawing shows the panel above the fireplace to line up with the outside of mantel legs. CHECK IN FIELD
  • Dimensions in between panels to be consistent; see revised drawing
  • Paint colors TBD. Emily please advise
Painting
  • Paint walls, trim on walls, ceiling at bar in Living Room, Trim at new doors install.
  • No window or door painting, separate from the front doors and Lanai doors
  • Please note that the new exterior door bids don't include paint, so MDG has an allowance in here to paint and stain the doors
Building Plans — Great Room / Family Room
Wet Bar Elevation 1/9
Wet Bar Cabinet Elevation
Prepared by: Beck/Allen Cabinetry (Kristine Factor)
Date: 7/8/2026  •  Scale: NTS
Full-height elevation showing (2) 18" wall cabinets, 33" wall cabinet, base cabinets, 24" fridge bay and roll-out drawer bank. Ceiling height 111" +/- under new soffit.
Wet bar cabinet elevation drawing
Great Room Wall Trim 1/2 & 2/2
Great Room Trim Elevations — Fireplace Wall & Bar / Living Room Wall
Scale: 1/4" = 1'-0"
One continuous trim package for the great room: the fireplace wall elevation (window trim, fireplace surround/mantel trim, wall panel layout — "A" dimension denotes distance between fireplace trim and window trim, to be held equal) and the bar / living room wall elevation.
Great room wall trim elevations, bar/living room wall and fireplace wall
Mantel Side Profile Build-Up McIntyre
Fireplace Mantel Side Profile Build-Up
Provided by: McIntyre
Red line marks the existing mantel; everything above the red line is new trim. Top shelf is 1-1/4" thick (?) (TBD on site) x 11-1/4" deep. Overall mantel height +/- 65".
Fireplace mantel side profile build-up, McIntyre
Great Room / Family Room — Products & Materials
Bar Area
Shiloh Scottsdale door front profile, shown in partial overlay for reference
Cabinetry
Wet Bar Cabinetry — Shiloh, Scottsdale Doorstyle
Photo shown: Partial Overlay (example only) Ordered: Full Overlay Alder / Whitesands Stain Softclose Ordered 7/8/2026 Expected Delivery 8/21/2026
Door profile shown (Scottsdale) is correct — but pictured in partial overlay for reference only. Actual wet bar cabinets are Framed Full Overlay. 9 glass shelves, 4 clear glass inserts, 4 wood mullion doors, 4 false decorative doors, (1) 3"H + (2) 7"H roll-out trays, 24" fridge appliance panel.
Whitesands Alder finish swatch
Finish reference:
Whitesands (Alder)
Zephyr Presrv beverage cooler
Refrigeration
Zephyr Presrv™ 5.6 Cu. Ft. Panel Ready Beverage Center
Model PRB24C01CPG 24" Single Zone Panel Ready
Full-extension wood rack, retractable glass quarter-shelf, 3-color LED lighting. Includes solid panel-ready door accessory (PRPNLC24A).
Nantucket SR1515 bar sink
Plumbing Fixtures
Nantucket SR1515 Pro Series 15" Square Undermount Bar/Prep Sink
Finish: Brushed Satin Stainless Ordered 7/17/2026
304 stainless steel construction, brushed satin finish, colander included. See technical specifications below.
Exterior Dimensions15" x 15"
Interior Dimensions13" x 13"
Exterior Height9"
Interior Bowl Depth9"
Drain Dimensions3.5" Standard drain opening (drain included)
Cabinet RequirementsFits 18" cabinet base minimum
Professional installation recommended
Gauge16
American Standard Delancey bar faucet, Brushed Cool Sunrise
Plumbing Fixtures
Model 4279410.GN0 Pull-Down Spray 1.5 GPM Finish: Brushed Cool Sunrise (Gold) Ordered 7/17/2026
Metal body/handle with brass swivel spout, ceramic disc valve cartridge, integral check valves, 28-3/4" braided supply hoses.
Schaub City Lights round multisided glass knob
Decorative Hardware
Model 55-SB Satin Brass 1-1/8"  •  Qty 13
Fireplace
Stoll Original Traditional fireplace doors, shown in Satin Brass
Fireplace Doors
Photo shown in Satin Brass Ordered Finish: Satin Gold Ordered 7/21/2026 Lead Time: 4–6 Weeks
Reference photo shows the Original Traditional door style in Satin Brass for door style/design only — actual doors are being ordered in Satin Gold (swatch below).
Satin Gold finish swatch
Actual finish reference:
Satin Gold
🪨
Item Pending
Category
Product / Material TBD
🎨
Item Pending
Category
Product / Material TBD

Doors — Scope of Work
Front Door
  • Most likely going with a stained door
  • Ryan bid white oak
  • Arched design inside door style vs. rectilinear
  • Flemish glass option possible
  • 3/4 glass panel as shown in inspiration picture
  • Arches inside door. OK by Ryan Bruning?
  • Client to visit showroom to select final stain color and Baldwin door hardware style and finish
  • Upon door selection approval, Jason to remove trim around front door for exact measures
  • Operating door to be on left when facing doors from exterior
Back Door
  • Ryan bid new, taller double doors to height of current semicircular transom (transom goes away). Approval TBD
  • New side lites in same openings
  • Operating door on right when looking at it from exterior
  • Full lite
  • Clad on exterior
  • Primed for paint on inside
  • Multi point lock
  • Hardware to be selected
  • Measurements taken: 100" from outside step to top of transom; 75" wide for the existing double doors; 17-1/4" wide existing sidelites
Door Installation
  • Remove existing door at main entry and install new door and trim
  • Remove existing door at kitchen to lanai and install new door and trim
  • Install hardware, (hinges, locksets and dead bolts) at rear hearthroom doors
  • Remove all debris from existing doors from site
  • Install Exterior door hardware at lanai
Living Room — Doors to Deck
  • Door hardware to coordinate what is being used on front door and lanai doors
  • TWO sets of passage with TWO deadbolts needed as there are TWO doors out to the deck area (initial estimate I believe only had 1 door)?
Building Plans — Doors
📐
Plans — Pending
Door plans and drawings will be added here once available.
Doors — Products & Materials
🚪
Item Pending
Category
Product / Material TBD
🔑
Item Pending
Category
Product / Material TBD
🪟
Item Pending
Category
Product / Material TBD

Exterior / Deck / Pool — Scope of Work
🔍 To be explored while on site during Phase 1 — scope, vendors and pricing TBD.
Exterior Grill Area
  • Grill area to be either covered with pavers (that match the tile in the screened porch
  • Or – Possible pedestal mounting system to bring the patio up to the same plane as the deck. Riser 7-1/4"
  • Or – Same Cool Deck coating as new spec for pool area
  • MDG need to evaluate these options. Call in someone from raised deck vendor?
  • Emily to dig up emails from Terbrock on where they had initially landed
Exterior Deck
  • MDG call an underdecking Rep to evaluate why it's leaking (holding water) in the cavity between the deck and underdecking system. May need new underdeck system
  • Recommend updates: new metal railing. Possible complete deck redo
  • ***Deck to be figured out first
Pool Deck / Area
  • Repaint Cool Deck coating on entire lower deck area
  • MDG call Jason @ Pool Specialists. They resurfaced the pool interior a couple of years ago. Check to see if they have any plans/dimensions
  • Emily to design built in countertop area between deck posts
  • Emily looking for blueprint house plans
  • Hot tub to be added to space
Building Plans — Exterior / Deck / Pool
📐
Plans — Pending
Exterior, deck and pool plans and drawings will be added here once available.
Exterior / Deck / Pool — Products & Materials
🧱
Item Pending
Category
Product / Material TBD
🏊
Item Pending
Category
Product / Material TBD
🛁
Item Pending
Category
Product / Material TBD